Nuclear Power Stocks in India 2026: Suppliers and Orders
India has run nuclear power stations since 1969, yet nuclear still makes up a small slice of its power system. In June 2026, India had 8,780 MW of nuclear capacity, just 1.60% of its total. The government now wants 22.38 GW by 2031-32 and 100 GW by 2047, and a new law passed in 2025 lets private Indian companies build and run nuclear plants for the first time.
Every one of those reactors needs pumps, special metals, precision parts, steam generators, turbines and civil works, and only a few Indian companies are qualified to supply them. This page lists the listed nuclear suppliers we have studied in depth, with each one's latest nuclear orders. Each row links to our full research on that company.
Figures as of 13 November 2026. This page is research, not a recommendation to buy or sell any stock.
Nuclear Power Stocks in India at a Glance
| Company | Where it sits | What it supplies | Nuclear orders (date) |
|---|---|---|---|
| KSB | Inside the reactor | Primary coolant pumps for heavy water reactors | ₹1,235 Cr on hand (Jun 2026) |
| Kirloskar Oil Engines | Outside the reactor | Emergency gensets: ten 6.3 MW sets for Kudankulam | ₹768 Cr NPCIL order (won 2024, 68-month programme) |
| MTAR Technologies | Inside the reactor | Fuel machining heads, drive mechanisms, core and coolant channel assemblies | ₹684 Cr civil nuclear order book (Jun 2026), incl. ₹504 Cr for Kaiga 5 & 6 |
| Unimech Aerospace | Reactor equipment | Support equipment and sub-assemblies for reactors | About ₹87 Cr won (Aug 2026), incl. ₹72.20 Cr for Tarapur 3 & 4 |
| Kilburn Engineering | Inside the plant | Coolers and heavy-water vapour-recovery systems | ₹57.11 Cr in the order book (Jun 2026) |
| MIDHANI | Materials | Special steels and alloys for reactor tubes, vessels and fittings | Part of ₹139 Cr of energy orders (1 Apr 2026) |
| Azad Engineering | Outside the reactor | Blades for nuclear steam turbines | Supply deals with Arabelle Solutions (EDF group) and GE Vernova's steam power arm |
| TARIL | Outside the reactor | Generator transformers for Kaiga 5 & 6 | First nuclear order (Aug 2026, value not disclosed) |
Nuclear orders are large and come in waves, so a single contract can be several years of a small company's nuclear revenue.
Inside and Outside the Reactor
A nuclear plant has two very different supply chains.
Inside the reactor building, every part must be qualified by NPCIL, India's nuclear power company, after years of trials. Few companies get through, so orders tend to go back to the same suppliers. KSB has supplied primary coolant pumps for India's heavy water reactors since the units at Narora. MTAR makes fuel machining heads and core assemblies, and Unimech and Kilburn supply equipment and systems around the reactor. MIDHANI makes the certified special metals.
Outside the reactor, the plant looks more like a large thermal power station: turbines, generators, transformers, gensets, pumps and civil works. Competition is wider here, but the orders are larger. Azad makes blades for nuclear steam turbines, TARIL supplies generator transformers, and Kirloskar Oil Engines makes the emergency gensets that keep the cooling running if the grid fails.
The Order Pipeline
The fleet of ten 700 MW reactors. In 2017, the government sanctioned ten 700 MW heavy water reactors at about ₹1,05,000 Cr, with close to ₹70,000 Cr of manufacturing orders going to Indian industry. The first fleet is planned at Kaiga, Gorakhpur, Chutka and Mahi Banswara.
The largest contracts so far. NPCIL gave the Kaiga 5 & 6 construction contract to Megha Engineering in April 2025 for ₹12,800 Cr, its biggest order ever. The four-unit Mahi Banswara plant, a joint venture of NPCIL and NTPC, is estimated at ₹42,000 Cr, and its nuclear island contract, tendered in July 2026, is worth over ₹28,000 Cr.
Private companies can now enter. The SHANTI Act of 2025 lets any company incorporated in India apply for a licence to build and run nuclear plants. It also removes the automatic right of an operator to claim damages from its suppliers after an accident, unless the contract says so.
Small reactors are next. The Nuclear Energy Mission, announced in the 2025-26 Budget, sets aside ₹20,000 Cr and aims to have at least five Indian-designed small modular reactors running by 2033.
Other Listed Companies in Nuclear Power
These companies also supply India's nuclear programme but are not yet covered in our in-depth research. The details come from their own filings, calls and releases.
| Company | Where it sits | Nuclear work |
|---|---|---|
| Larsen & Toubro | Inside the reactor | Steam generators: delivered the full set of four for Kaiga 5 & 6, and dispatched its 7th 700 MW steam generator by April 2026 |
| BHEL | Outside the reactor | ₹10,800 Cr turbine island order for six 700 MW units (2021) and 12 steam generators |
| Walchandnagar Industries | Inside the reactor | Calandrias, end shields and reactor headers |
| Ratnamani Metals & Tubes | Materials | Nuclear-grade stainless steel tubes approved by NPCIL |
| Kirloskar Brothers | Inside and outside | Sodium pumps for the fast breeder reactor, secondary-circuit pumps |
| HCC | Civil works | Says it has built 60% of India's installed nuclear capacity |
| Power Mech Projects | Civil works | Turbine-island civil and structural work at Kaiga |
| NTPC | Owner | 49% partner in the Mahi Banswara 4 x 700 MW plant |
How to Read a Nuclear Supplier's Order Book
- Inside or outside the reactor? Parts inside the reactor need long qualification and face few competitors; parts outside face more.
- How long is the execution? Nuclear orders can run for four to six years; KSB, for example, delivers a main coolant pump about 48 months after the order. A large order may add only a little revenue each year.
- Who is the customer? Most orders come from NPCIL or its main contractors. Check whether the order is direct or through an EPC company.
- What share of revenue is nuclear? For most suppliers, nuclear is a small part of today's revenue. The order book shows where it could go.
- Is the project on time? Supplier revenue follows the reactor's schedule. Delays at site delay deliveries and payments.
Key Risks for Nuclear Stocks
- Targets have slipped before: India once aimed for 20 GW of nuclear power by 2020. It had 8.78 GW in June 2026.
- Long build times: India's roadmap for 100 GW puts a new plant at about 11-12 years from state consent to completion. Kudankulam 3 & 4, once due in 2026, are now expected in 2027.
- Lumpy orders: contracts come in large, rare batches, so suppliers' nuclear revenue can rise and fall sharply.
- Fuel imports: about 69% of NPCIL's generation in 2024-25 came from reactors running on imported uranium.
- Rules still being written: the SHANTI Act's rules were released only as a draft in August 2026, and tariffs for new plants are expected to be higher than for today's older fleet.
Explore our Products
Research Framework
Emerging Titans
Combination of quantitative analysis, industry tailwinds, and management assessment - SPRINT investment philosophy
Tiny Titans
Heavy emphasis on scuttlebutt research, plant visits, and early on-ground signals
Conclusion
India's nuclear plans are the largest in its history, and the first big contracts of the 700 MW fleet are now in suppliers' order books. But the programme has a long record of slipping timelines, and each order takes years to turn into revenue. Use the tables above to see where each company sits, then read our research on each one for its orders, capacity and risks.
FAQs
Which are the nuclear power stocks in India?
+Listed companies that supply India's nuclear programme include KSB, MTAR Technologies, Kirloskar Oil Engines, Unimech Aerospace, Kilburn Engineering, MIDHANI, Azad Engineering and TARIL, along with larger groups such as L&T and BHEL. The tables on this page list what each one supplies.
How much nuclear power does India have?
+India had 8,780 MW of nuclear capacity in June 2026, about 1.60% of its total power capacity. The government aims for 22.38 GW by 2031-32 and 100 GW by 2047.
Can private companies build nuclear plants in India?
+Yes. The SHANTI Act of 2025 allows any company incorporated in India to apply for a licence to build and operate nuclear plants. The detailed rules were released as a draft in August 2026.
Which company makes the coolant pumps for India's nuclear reactors?
+KSB has supplied the primary coolant pumps for India's heavy water reactors since the units at Narora. It held ₹1,235 Cr of nuclear orders in June 2026.
What are small modular reactors?
+Small modular reactors are smaller nuclear reactors that can be built in factories and installed in less time. India's Nuclear Energy Mission sets aside ₹20,000 Cr and aims for at least five Indian-designed ones by 2033.
What are the risks in nuclear power stocks?
+Nuclear targets have slipped in the past, plants take many years to build, orders are large but rare, India imports much of its uranium, and the rules under the new law are still being finalised.
Explore our Products
Research Framework
Emerging Titans
Combination of quantitative analysis, industry tailwinds, and management assessment - SPRINT investment philosophy
Tiny Titans
Heavy emphasis on scuttlebutt research, plant visits, and early on-ground signals
Modern Warfare to Multibaggers
Key Trends. Strategic Shifts. Opportunities Ahead.
Don't Miss This Exclusive Webinar!
Join Value Educator to decode the key trends shaping India's defence sector and learn how to identify tomorrow's potential leaders in the space.
- In-depth research on India's defence sector
- Live Q&A session
- Actionable takeaways for long-term investors

No comments yet. Be the first to comment!